Report on Approved Ongoing and Completed Schemes under Tourism  Engineering Cell as on 30th May 2014
SLNo Name of the completed schemes against which payment has not been settled Approved estimated in Rupees  Tendered amount in Rupees Date of approval Head of Account Date of commencement Proposed date of completion Physical progress of work in % Gross value of work bill including difference of cost in lakhs Deduction on account of Departmental materials / hiring charges of roller Fund required for payment of Agency bill, Income Tax, Vat , Royalty, Security Deposit & Cess Fund already released by Finance Department Fund already released by other Department Balance fund to be released for settlement of work bill Remarks
1 RCC lining of the Lake base and internal side wall  at Goke 15,039,549.00 17,971,538.00 01.06.2011 SCA 06.07.2011 05.07.2012 100.00% ######### 0.00 ######### ######### 0.00 ######### Final Bill Under process
2 Extension of Catch Water Drain from Boating Lake and surrounding areas at Jamuney, Goke . 1,312,260.00 1,312,260.00 27.0202013 SCA 21.03.2013 20.04.2013 100.00% ######### 0.00 ######### 0.00 0.00 ######### Final Bill Under process
3 Construction of M.S. Grill Fencing Boating lake at Jamuney Goke.  1,193,317.00 1,193,317.00 27.02.2013 SCA 21.03.2013 20.04.2013 100.00% ######### 0.00 ######### 0.00 0.00 ######### Final Bill Under process
4 Construction of Concrete Gallery at other side of Arch Bridge at Jamuney , Goke.  3,757,282.00 3,757,282.00 27.02.2013 SCA 21.03.2013 20.04.2013 100.00% ######### 0.00 ######### 0.00 0.00 ######### Final Bill Under process
5 "Construction of Pavement work with Coloured decorative paver block and  brick work flower  bed around Boating Lake at Jamuney, Goke." 6,500,433.00 6,393,333.00 27.02.2013 SCA 21.03.2013 20.06.2013 100.00% ######### 0.00 ######### 0.00 0.00 ######### Final Bill Under process
6 Repainting Restaurant Building, galleries, replacement of broken glass panes and decorative wall finish at Jamuney, Goke. 136,708.00 136,708.00 27.02.2013 SCA 21.03.2013 20.04.2013 100.00% 136,708.00 0.00 136,708.00 0.00 0.00 136,708.00 Final Bill Under process
7 Construction of Riverside Concrete Gallery at Jamuney Park, Goke. 889,795.00 889,617.00 3/26/2013 SCA 26.04.2013 7/25/2013 100.00% 879,559.00 0.00 879,559.00 0.00 0.00 879,559.00 Final Bill submitted
8 Decorative wall finish,  flower pot on wall top and allied works below Happy New Year Bridge at Jamuney, Goke. 954,526.00 954,526.00 2.04.2013 SCA 2.05.2013 1.07.2013 100.00% 947,464.00 0.00 947,464.00 0.00 0.00 947,464.00 work in progress
9 Construction of Lakeside garden near Boating Lake at Jamuney, Goke. 6,341,630.00 6,341,630.00 20.03.2013 SCA 2.05.2013 1.082013 100.00% ######### 0.00 ######### 0.00 0.00 ######### Final Bill submitted
10 Construction of Open Air Theatre at Chowrasta, Darjeeling 27,334,260 32,418,432 12.12.11 SCA 20.01.12 20.07.13 92% 18,652,569 0.00 18,652,569 15,747,794 0.00 2,904,775 work in progress
11 Construction of Dancing Platform with Non-skid Tiles flooring at Jamuney, Goke. 360,980 360,980 27.02.2013 SCA 21.03.2013 20.04.2013 95% 342,931 0.00 342,931 0.00 0.00 342,931 work in progress
12 Construction of Catch water drain, jhora, breast wall at Devitar, Jamuney, Goke. 7,175,886 7,175,168 27.02.2013 SCA 21.03.2013 20.07.2013 65% 2,511,309 0.00 2,511,309 0.00 0.00 2,511,309 work in progress
13 Construction of Mini Car Park and Pavilion side Breast wall at Januney, Goke. 8,146,807 8,145,992 27.02.2013 SCA 21.03.2013 20.07.2013 100% 7,331,393 0.00 7,331,393 0.00 0.00 7,331,393 Final Bill submitted
14 River Bank Protection work at Water Kingdom side at Jamuney Park, Goke 21,291,000 20,775,791   SCA    26.04.2013 25.10.2013 70% 14,543,054 0.00 14,543,054 0.00 0.00 14,543,054 work in progress
15 Construction of swimming pool at Goke ( Big) 8,332,813 7,936,009 08.12.2011 SCA 15.03.2012 14.03.2013 20% 1,587,202 0.00 1,587,202 0.00 0.00 1,587,202 Advance payment as per agreement not released due to which progress of work unsatisfactory
16 Construction of swimming pool at Goke ( Small) 4,817,149 4,817,149 08.12.2011 SCA 15.03.2012 15.11.2012 0% 0 0.00 0 0.00 0.00 0
17 Supply order for filtration Unit for swimming pool ( small) 1,334,502 1,334,502 08.12.2011 SCA 27.03.2012 15.11.2012 0% 0 0.00 0 0.00 0.00 0
18 Supply order for filtration Unit for swimming pool (Big) 2,909,924 2,909,924 08.12.2011 SCA 27.03.2012 0.00 0% 0 0.00 0 0.00 0.00 0
19 Construction of 23 bedded Guest House at Goke 27,776,834 27,776,834 18.10.2011 SCA 13.12.2011 13.12.2013 40% 11,110,734 0.00 11,110,734 11,110,734 0.00 0 work in progress
20 Construction of Tourism Resort at Jamuni,Darjeeling, Gorkhaland Territorial Administration Phase -I 62,931,602 74,888,606 20.12.2012   22.02.2013 21.08.2014 35% 7,488,861 0.00 7,488,861 0.00 0.00 7,488,861 work in progress
21 Painting of M.S. Railing,Benches,Ticket Counter maintenance of Hawaghar and minor repair of Ganga Maya Park and Rock Garden Barbottay Darjeeling. 625,114 595,228 23.10.2013 SPGS 09.01.2014 8.04.2014 100%             Final Bill submitted
22 Construciton of 3 nos of Bollywood site Development at Lalkothi,Chowrasta & Jamuney under GTA 1,642,905 1,642,741 10.04.2013 SCA 04/01/2013 3.4.2013 100% 985,645 0.00 985,645 0.00 0.00 985,645 Final Bill submitted
23 Construction of Multi-Level Car Parking at DRC, Darjeeling. 61,940,992 61,940,992 12.12.11   01.10.12 (date of possession of work site)  1.01.2015 80% 49,552,794 0.00 49,552,794 ######### 0.00 0.00 work in progress